how many weeks dose it take for a civil engineer to make a design??
im working on a steam essay on skyscrapers
Login to comment
5 answers
Updated
Trevor’s Answer
Hi Illiana! What a fun topic for a STEAM essay. The short answer: it depends on how big and complicated the project is. A skyscraper design usually takes months to a few years, not weeks.
Rough timelines by project size
Small projects like a sidewalk, a small retaining wall, or a parking lot: a few weeks
Medium projects like a small bridge, an office building, or a school: several months to a year
Skyscrapers: often 1–3 years or more of design work before construction starts. The most famous towers, like the Burj Khalifa, took years to design.
Why skyscrapers take so long A skyscraper isn't designed by one person. It takes a big team, including architects, structural engineers, civil engineers, geotechnical (soil) engineers, and mechanical and electrical engineers. They work through these phases:
Concept design: Choosing the shape, height, and basic structure.
Schematic design: Picking the structural system, such as a steel frame, a concrete core, or both.
Detailed design: Calculating loads, beam and column sizes, foundations, and connections.
Testing and analysis: Running computer models and wind tunnel tests, because wind is one of the biggest forces on tall buildings. Engineers also design for earthquakes.
Permits and reviews: City officials check that the design meets building codes. This alone can take months.
Changes during construction: Engineers keep adjusting the design as problems come up.
What civil and structural engineers think about for skyscrapers
Foundations: Deep piles or caissons that reach strong soil or bedrock.
Gravity loads: The weight of the building, people, and furniture.
Wind and sway: Some towers use huge "tuned mass dampers," like the giant swinging ball in Taipei 101, to cut down on swaying.
Earthquakes: Flexible designs that bend without breaking.
Safety: Fire protection, exits, and elevators.
Ideas for your essay
Compare how long design takes with how long construction takes.
Explain how computers and 3D modeling (BIM) have sped up the design process.
Show the STEAM connection: science (forces), technology (software), engineering (structure), art (architecture and appearance), and math (load calculations).
Good luck with your essay, Illiana!
Rough timelines by project size
Small projects like a sidewalk, a small retaining wall, or a parking lot: a few weeks
Medium projects like a small bridge, an office building, or a school: several months to a year
Skyscrapers: often 1–3 years or more of design work before construction starts. The most famous towers, like the Burj Khalifa, took years to design.
Why skyscrapers take so long A skyscraper isn't designed by one person. It takes a big team, including architects, structural engineers, civil engineers, geotechnical (soil) engineers, and mechanical and electrical engineers. They work through these phases:
Concept design: Choosing the shape, height, and basic structure.
Schematic design: Picking the structural system, such as a steel frame, a concrete core, or both.
Detailed design: Calculating loads, beam and column sizes, foundations, and connections.
Testing and analysis: Running computer models and wind tunnel tests, because wind is one of the biggest forces on tall buildings. Engineers also design for earthquakes.
Permits and reviews: City officials check that the design meets building codes. This alone can take months.
Changes during construction: Engineers keep adjusting the design as problems come up.
What civil and structural engineers think about for skyscrapers
Foundations: Deep piles or caissons that reach strong soil or bedrock.
Gravity loads: The weight of the building, people, and furniture.
Wind and sway: Some towers use huge "tuned mass dampers," like the giant swinging ball in Taipei 101, to cut down on swaying.
Earthquakes: Flexible designs that bend without breaking.
Safety: Fire protection, exits, and elevators.
Ideas for your essay
Compare how long design takes with how long construction takes.
Explain how computers and 3D modeling (BIM) have sped up the design process.
Show the STEAM connection: science (forces), technology (software), engineering (structure), art (architecture and appearance), and math (load calculations).
Good luck with your essay, Illiana!
Updated
William’s Answer
High Illiana,
It's a pleasure taking this opportunity to respond to your question.
One way of approaching your assignment is to run it as a project.
The first phase is the Initiation phase. The need for the project is identified at this stage. Business Case/Feasibility of the project is established during this phase. Key Deliverables are also defined during this process.
The next phase is Planning. A functional design is done based on the concepts for functionality. Detailed design follows the conceptual design. Overriding considerations are Reliability, Availability, Maintainability and Safety. A risk assessment is important too. Resource requirements are then established (time, manpower, materials, tools, equipment, skills). Activities can then be scheduled (Gantt chart).
The project then proceeds to the Execution phase. This phase is usually split into two: Build phase & Operationalization.
The Build phase is basically construction/manufacture of the product. Compliance to Design & Construction Codes is essential at this stage. Once construction is complete, commissioning is undertaken. Successful completion of commissioning means Beneficial Occupation can take place. This is the Operationalization phase. The product is then put into service at this stage. Standard Operating Procedures (SOPs) and Maintenance Schedules are developed and rolled out. Relevant training for the operating & maintenance crew is conducted.
The final phase is Project Close Out. Post Project Review takes place to establish what went well and what needs to improve. Learnings are incorporated into project methodology as a way of creating improvement. Financial review, too, is conducted. Project team relinquishes ownership of the project at this point.
It's a pleasure taking this opportunity to respond to your question.
One way of approaching your assignment is to run it as a project.
The first phase is the Initiation phase. The need for the project is identified at this stage. Business Case/Feasibility of the project is established during this phase. Key Deliverables are also defined during this process.
The next phase is Planning. A functional design is done based on the concepts for functionality. Detailed design follows the conceptual design. Overriding considerations are Reliability, Availability, Maintainability and Safety. A risk assessment is important too. Resource requirements are then established (time, manpower, materials, tools, equipment, skills). Activities can then be scheduled (Gantt chart).
The project then proceeds to the Execution phase. This phase is usually split into two: Build phase & Operationalization.
The Build phase is basically construction/manufacture of the product. Compliance to Design & Construction Codes is essential at this stage. Once construction is complete, commissioning is undertaken. Successful completion of commissioning means Beneficial Occupation can take place. This is the Operationalization phase. The product is then put into service at this stage. Standard Operating Procedures (SOPs) and Maintenance Schedules are developed and rolled out. Relevant training for the operating & maintenance crew is conducted.
The final phase is Project Close Out. Post Project Review takes place to establish what went well and what needs to improve. Learnings are incorporated into project methodology as a way of creating improvement. Financial review, too, is conducted. Project team relinquishes ownership of the project at this point.
Updated
Teklemuz’s Answer
Designing a skyscraper is a long journey, often taking months or even years, but it's an exciting process. Structural engineers work hard to make sure everything is perfect. They think about how tall the building will be, what materials to use, and how to keep it safe from wind and earthquakes. The time it takes also depends on how much planning and teamwork are needed. For instance, the Burj Khalifa and Taipei 101 each use unique methods to handle wind and movement. This shows how creative and adaptable engineers can be.
Updated
LeTroy’s Answer
To complete a design using CAD software, you typically go through three phases: boxout, secondary forms, and final details.
1. In the boxout phase, start by creating the main structure. For a skyscraper, this includes the beams, foundation, wall placeholders, elevator shaft, elevator, and apartment spaces.
2. Next, move to the secondary forms. Add doors, detailed windows and frames, flooring, elevator outlines, and landscaping details.
3. In the final phase, enhance your design with textures using visualization or texture mapping. Refine all static components, and add furnishings and small details to elevate your design.
The time needed can vary widely, from a week to a year, depending on your commitment and the time you dedicate to the project.
1. In the boxout phase, start by creating the main structure. For a skyscraper, this includes the beams, foundation, wall placeholders, elevator shaft, elevator, and apartment spaces.
2. Next, move to the secondary forms. Add doors, detailed windows and frames, flooring, elevator outlines, and landscaping details.
3. In the final phase, enhance your design with textures using visualization or texture mapping. Refine all static components, and add furnishings and small details to elevate your design.
The time needed can vary widely, from a week to a year, depending on your commitment and the time you dedicate to the project.
Updated
Robert’s Answer
For any building, the typical A/E Team is the Architect as 'Prime' ---they do the coordination and overall design concept.
They work with a civil engineer and their in-house designers to come up with a model, both 3D digital and often 3D printed. The model is like a movie set, it looks real but it's hollow inside. 'Talking Paper' for all of the people who will have to provide a service and make an approval.
After the potential client has made their design concept comments and had them incorporated into the design by the Architect and Civil, the Architect will employ an outside Estimating Expert, and provide a count of the units of space and height and composition for unit cost pricing, based on current and expected construction market and lending costs. The client has to know upfront what this is likely to cost. It's a gamble!
The Architect consults with their Structural, Mechanical and Electrical teams for their proposed consultant fees, added to the Cost Estimate, added to the Architect's fees, a Contingency Cost Overrun percentage, taxes, utilities hookups, permits, and provides the client with a proposed Cost per Occupied Space or 'BOMA'.
From this, the client can determine the lease or sale cost per square feet, including loan fees, to see if the proposed units are within the acceptable real estate market range. Say the estimate is $675 an occupied square foot, and $400 per square foot to $800 square foot of occupied unit might be the 'do-able' market range. The client meets with their bank, real estate agents, insurers and makes a decision whether to go forward. It's sounds good at $675. Pull the trigger!
The next phase after approval and award Notice to Proceed, the Architect/Engineer (A/E) team does a Front End Engineering Design (FEED) to reach a feasible design and do 'look-ahead loss-prevention'. Maybe they find the foundation will be more difficult than the first Estimate, or there may be Planning issues with the height or even shading or blocking views. Or steel is suddenly more expensive because of supply shortage. That's factored into the first estimate. At this point, the client can feel comfortable there is a high likelihood that the project is viable, if those changes were not too large.
If it turns out not to be, if it is running $875 now, (which would be a major error) this is called the client's 'sunk cost' and the project is cancelled. The client would demand some portion of those sunk costs back as A/E Errors & Omissions (E&O) because of the huge $675->$875 mistake. Let's assume is was only 8% higher, we're still in the $400 to $800 range and the client sharpens their financial numbers. Still a 'go'.
You can see though, we're only 15% of the way through the project! It's been months of meetings with a large team of people. If the FEED looks good, costs are stable, then the Architect will schedule a Pre-Approval meeting with the Agency Having Jurisdiction (AHJ), now that the design is solidified in detail, and they can go through all the utilities, traffic, parking, pedestrian, sometimes LEED, agency concerns, to determine the associated permitting fees (that were already generally estimated back in the first stage). If there's a 'show stopper' now, everything stops while the client, the Architect and the AHJ figure out a common agreeable solution. Maybe a canopy over the side walk, or a second service entrance, things like that, sometimes in business or high-end commercial, the AHJ will demand fancy veneers or expensive area lighting. It's all argued out.
So, wow, months and months and where's the cost now? The AHJ wants $1,000,000 worth of French veneer and area lights made in Italy! The Client though, has a promise from the AHJ that's all the added agreed costs will be. They sharpen their pencils again, and give Notice to Proceed.
The team now has all the preliminaryh approvals, and works towards a 35% Issued for Approval plan set, that 'locks' the design. Then 65% Issued for Approval 'locks' the details. Now the client is starting to line up their own Engineering, Planning and Construction (EPC) team to work on the construction side of the project. From 65% to 85% phase the A/E and EPC work tightly together to issue a thick plan set for permitting, for each discipline Civil Contractor, Structural Contractor, Mechanical Contractor, Electrical Contractor, Control Systems Contractor, and start taking preliminary bids and see who is available, and who has the necessary labor and equipment within the planned schedule.
Generally they two teams will will leave some items to resolve in the field as they arise, as a Change Order (CO) because time is money. So the plan set may be we would call only 85% to 95% complete, but everyone is a professional and that's enough progress to get permitting and bids.
The first phase is the Civil Site Work where the project Civil Engineer will often have an observer during the foundation excavation, in case there are any 'surprises'. Sometimes decisions have to be made on an emergency basis, say if there's a sinkhole or water bubbling up from the ground.
So for your STEAM project, your Civil Engineer is first in at FEED stage to layout the site around the building, and first in the Construction stage, but it's a lot like playing volleyball, weeks or months go by where someone else has the ball. No phone calls means your discipline isn't needed now, ---but you still have to have your Civil designers and engineers available, often for years with a skyscraper.
They work with a civil engineer and their in-house designers to come up with a model, both 3D digital and often 3D printed. The model is like a movie set, it looks real but it's hollow inside. 'Talking Paper' for all of the people who will have to provide a service and make an approval.
After the potential client has made their design concept comments and had them incorporated into the design by the Architect and Civil, the Architect will employ an outside Estimating Expert, and provide a count of the units of space and height and composition for unit cost pricing, based on current and expected construction market and lending costs. The client has to know upfront what this is likely to cost. It's a gamble!
The Architect consults with their Structural, Mechanical and Electrical teams for their proposed consultant fees, added to the Cost Estimate, added to the Architect's fees, a Contingency Cost Overrun percentage, taxes, utilities hookups, permits, and provides the client with a proposed Cost per Occupied Space or 'BOMA'.
From this, the client can determine the lease or sale cost per square feet, including loan fees, to see if the proposed units are within the acceptable real estate market range. Say the estimate is $675 an occupied square foot, and $400 per square foot to $800 square foot of occupied unit might be the 'do-able' market range. The client meets with their bank, real estate agents, insurers and makes a decision whether to go forward. It's sounds good at $675. Pull the trigger!
The next phase after approval and award Notice to Proceed, the Architect/Engineer (A/E) team does a Front End Engineering Design (FEED) to reach a feasible design and do 'look-ahead loss-prevention'. Maybe they find the foundation will be more difficult than the first Estimate, or there may be Planning issues with the height or even shading or blocking views. Or steel is suddenly more expensive because of supply shortage. That's factored into the first estimate. At this point, the client can feel comfortable there is a high likelihood that the project is viable, if those changes were not too large.
If it turns out not to be, if it is running $875 now, (which would be a major error) this is called the client's 'sunk cost' and the project is cancelled. The client would demand some portion of those sunk costs back as A/E Errors & Omissions (E&O) because of the huge $675->$875 mistake. Let's assume is was only 8% higher, we're still in the $400 to $800 range and the client sharpens their financial numbers. Still a 'go'.
You can see though, we're only 15% of the way through the project! It's been months of meetings with a large team of people. If the FEED looks good, costs are stable, then the Architect will schedule a Pre-Approval meeting with the Agency Having Jurisdiction (AHJ), now that the design is solidified in detail, and they can go through all the utilities, traffic, parking, pedestrian, sometimes LEED, agency concerns, to determine the associated permitting fees (that were already generally estimated back in the first stage). If there's a 'show stopper' now, everything stops while the client, the Architect and the AHJ figure out a common agreeable solution. Maybe a canopy over the side walk, or a second service entrance, things like that, sometimes in business or high-end commercial, the AHJ will demand fancy veneers or expensive area lighting. It's all argued out.
So, wow, months and months and where's the cost now? The AHJ wants $1,000,000 worth of French veneer and area lights made in Italy! The Client though, has a promise from the AHJ that's all the added agreed costs will be. They sharpen their pencils again, and give Notice to Proceed.
The team now has all the preliminaryh approvals, and works towards a 35% Issued for Approval plan set, that 'locks' the design. Then 65% Issued for Approval 'locks' the details. Now the client is starting to line up their own Engineering, Planning and Construction (EPC) team to work on the construction side of the project. From 65% to 85% phase the A/E and EPC work tightly together to issue a thick plan set for permitting, for each discipline Civil Contractor, Structural Contractor, Mechanical Contractor, Electrical Contractor, Control Systems Contractor, and start taking preliminary bids and see who is available, and who has the necessary labor and equipment within the planned schedule.
Generally they two teams will will leave some items to resolve in the field as they arise, as a Change Order (CO) because time is money. So the plan set may be we would call only 85% to 95% complete, but everyone is a professional and that's enough progress to get permitting and bids.
The first phase is the Civil Site Work where the project Civil Engineer will often have an observer during the foundation excavation, in case there are any 'surprises'. Sometimes decisions have to be made on an emergency basis, say if there's a sinkhole or water bubbling up from the ground.
So for your STEAM project, your Civil Engineer is first in at FEED stage to layout the site around the building, and first in the Construction stage, but it's a lot like playing volleyball, weeks or months go by where someone else has the ball. No phone calls means your discipline isn't needed now, ---but you still have to have your Civil designers and engineers available, often for years with a skyscraper.